Undermount Slides
Ball Bearing Slides
Hinges
 
 
Push Open and Soft Closing Undermount Slide 1A88/1B88

【Cabinet evaluation check】
(1)
‧Ensure that the difference for the cabinet internal width and drawer internal width is within the tolerance of 42mm for the 1A88.
‧ Ensure that the difference for the cabinet internal width and drawer internal width is within the tolerance of 49mm for the 1B88.
 
Example:
‧ 1A88: cabinet internal width of 500mm with the corresponding drawer inner width of 457-458mm.
‧ 1B88: cabinet internal width of 500mm with the corresponding drawer inner width of 451mm.
   
Cabinet evaluation check
(2)
Cabinet internal width should be consistent all the way out.
(3)
The bottom recess cannot exceed 13mm
(4)
Drawer must be in perfect rectangular shape.
(5)
Drawer sub front must set tight against drawer front panel.
 
* Inconsistency of the cabinet internal width and the dimension precision will have negative effect to push open function.
* Incorrect drawer front installation will also have negative effect to push open function.
Cabinet evaluation check
 
【Front View】
Front View
 
【Side View】
Side View
 
* Ensure the installation location or the cabinet is on a flat surface.
 
Inset installation Formula
X
18
19
20
21
22
23
24
Y
59
60
61
62
63
64
65
Z
26
27
28
29
30
31
32
 L : Slide Length X : Front Panel Thickness
 
【Drawer installation guide】
(1)
Hole Drilling
(2)
Locking Device Installation
   
Drawer installation guide
 
【Cabinet installation procedures】
(1)
Draw base line and prepare drawer rear positional hole drilling .
 
* It is not recommended to drill the drawer rear positioning hole on the top of the slide, as the wooden residual may stuck on the grease and therefore affect the cabinet’s functionality.
   
Cabinet installation procedures
(2)
Ensure the pair of slides is installed on level and symmetrical on both sides.
(3)
Insert the drawer until locking device clicks.
   
Cabinet installation procedures
 
* After inserting the drawer, checking if fine tuning is needed before putting on drawer front panel.
   
【Guidance of fine tuning adjustment】
The slide function can be fine turned with minor adjustment. If the issues still exist after the adjustment, please reset to factory default setting and ensure each installation dimension is in accordance with the specification.
Guidance of fine tuning adjustment
 
After assembly is completed, if the mechanism does not function fully as expected, please check the following items:
【Cabinet Self-Assessment】
1.
The cabinet and drawer must be in perfect rectangular shape, ensure that they are not in diamond or trapezoid shape.
2.

Check the consistency of the side space (clearance), depth, and level is identical between the right and left.

3.

Ensure the locking device is correctly installed.

4.
Ensure the drawer dimension listed below is correct.
1 Rear positioning hole.
2 Consistency of drawer internal width
3 Drawer side bottom protrusion.

Push-Open Undermount Slide 1A89/1B89
【Installation Instruction】
1.
Before installing the slides, make sure the dimensions of the cabinet and drawer meet the requirements specified in Fig. 1 and 2.
2.
Drill holes on the cabinet following the 'Cabinet Holes Position' drawing on the reverse page. Mount the slides on the cabinet using the recommended type of screws.
3.
Make cut-outs on the drawer according to Fig. 3A and Fig. 3B's dimension (Using the drill template FL00ZD0-A as page 1.39 is recommended), then install the front release lever according to Fig. 3A.
4.
Pull out the slides on the cabinet.
 
【Front View】
Front View
 
【Side View】
Side View
 
* Ensure the installation location or the cabinet is on a flat surface.
 
Inset installation Formula
X
18
19
20
21
22
23
24
Y
59
60
61
62
63
64
65
Z
26
27
28
29
30
31
32
 L : Slide Length X : Front Panel Thickness
 
【Installation Requirement】
Installation Requirement
 
5.
Position and align the drawer with the slide as shown in Figs. 4A and 4B. Push the drawer all the way into the cabinet as shown in Fig. 4C until clicked to complete the installation.
6.
After confirming the drawer is operating normally, install the front panel.
7.
If height / depth adjustment is needed after installation, please refer to the Detail Adjustment Info. below or the feature diagram on the previous page.
 
Installation Requirement
 
【Detail Adjustment Info】
Detail Adjustment Info
 
【Notes for installation】
1.
Ensure the drawer body appearance is upright. It could not be diamond trapezoidal or distorted!
2.
Ensure the side space, depth on both sides are consistent.
3.
Ensure the installation location or the cabinet is on a flat surface.
4.
Ensure the front release lever is installed correctly.
5.
Ensure the drawer dimensions, rear notch locking hole, internal drawer width, and the drawer bottom recess are correct.
 
   
 
SIMPLEX- Silent Soft-Closing Undermount Slide 1A68/1B68 Cabinet evaluation check
‧ Ensure that the difference for the cabinet internal width and drawer internal width is within the tolerance of 42mm~43mm for the 1A68/1B68.
【Cabinet evaluation check】
(1) Example: Cabinet internal width of 500mm with the corresponding drawer inner width of 457-458mm.
(2) Cabinet internal width should be consistent all the way out.
(3) Drawer must be in perfect rectangular shape.
Cabinet evaluation check
Cabinet evaluation check
【Front View】
Front View 
【Side View】
Side View
Inset installation Formula
X
18
19
20
21
22
23
24
Y
59
60
61
62
63
64
65
Z
26
27
28
29
30
31
32
 L : Slide Length X : Front Panel Thickness
 
   
【Drawer installation guide】
(1)
Hole Drilling
(2)
Locking Device Installation
   
 Drawer installation guide 
【Cabinet installation procedures】
(1) Drawer base line and preparing drawer rear positional hole drilling.
* It is not recommended to mount on to slide without predrilling, as the wooden residual may stuck on the grease and therefore negatively affect the cabinet’s functionality.
Cabinet installation procedures
(2)
Ensure the pair of slides is installed leveled and symmetrical on both sides.
(3)
Insert the drawer until locking device clicks.
  * After inserting the drawer, checking if fine tuning is needed before putting on drawer front penal.
   
 【Guidance of fine tuning adjustment】
Tool-less Height Adjustment :
Simply rotate the wheel at the front bottom of the drawer to adjust the drawer height.
Guidance of fine tuning adjustment 【Cabinet evaluation check list】
After assembly is completed, if the mechanism is not fully functional, please check the following items.
(1) The cabinet and drawer must be in perfect rectangular shape, ensure that they are not in diamond or trapezoid shape.
(2) Check the consistency in side space (clearance), depth, and level is the identical in the right and left hand side.
(3) Ensure the locking device is correctly installed.
(4) Ensure the drawer dimension listed below is correct.
‧ Rear positioning hole
‧ Drawer internal width
‧ Drawer bottom protrusion
  

  
 
Silent Soft-Closing 3M52/3J52
Cabinet Design
Cabinet Design
Ensure that the difference for the cabinet internal width and drawer internal width is within the tolerance of 26mm
Example:
Cabinet internal width500mm-26mm=474mm
Drawer width=474mm
 
1. Ensure that the cabinet and drawer installation is accurate
Cabinet Design  
 
1.
Cabinet internal width should be consistent all the way out.(Fig.1)
2.
Ensure that the drawer front and rear width are equal.(Filg.2)
3.
Ensure that the drawer diagonal are equal.(Fig.3)
   
2. Drawer base line
 
Make sure both cabinet members are vertically and horizontally parallel.(Filg.4)
Drawer base line  
3. Locked the inner member
 
Inner rail snapping the center tap and the screw holes align baseline.
(Fig.5)-(Fig.6)
  Locked the inner member  
 
4. Locked the intermediate member & outer member
  1. Align the outer member and the intermediate member with the baseline.
2.The distance between outer members and the cabinet should be the same. (Fig.7)-(Fig.8)
Locked the intermediate member & outer member  
 
  Locked the intermediate member & outer member  
 
 
5. Push forward the Ball Retainer
 
Push the ball retainers between the outer members and the intermediate members to the forefront.(Fig.9)
  Push forward the Ball Retainer  
 
 
6. Insert drawer into the cabinet
 
Insert drawer members into cabinet members as indicated and push the drawer until is closed.(Fig.10)
  Insert drawer into the cabinet  
 
 
 
【Cabinet evaluation check】
 
Check the spacing on both sides of the assembled:
Please check the 12.7~13.4 if press open the drawer not smooth movement. (Fig.12)
  Cabinet evaluation check  
 
   
 
Push-Open Ball Bearing Slides 3M89/3J89
Cabinet Design
Cabinet Design
  Ensure that the difference for the cabinet internal width and drawer internal width is within the tolerance of 26mm
Example:
Cabinet internal width 500mm-26mm=474mm
Outside width drawer 474mm

‧Wide cabinet design principles:
  Push-Open Ball Bearing Slides (1A89, 3M89, 3J89, AE89)Recommendations drawer aspect ratio of 2: 1. (Fig.1-Fig.2)
  Wide cabinet design principles
 
(1) Ensure that the cabinet and drawer installation is accurate. Wide cabinet design principles
  1. Cabinet internal width should be consistent all the way out(Fig.3)
2. Ensure that the drawer front and rear width are equal (Fig.4)
3. Ensure that the drawer diagonal are equal(Fig.5)
 
Wide cabinet design principles
 
(2) Drawer base line Drawer base line
  Make sure both cabinet members are vertically and horizontally parallel.
(Fig.6)
 
(3) Locked the inner member
  1. Align the outer member and the intermediate member with the baseline.
2.The distance between outer members and the cabinet should be the same. (Fig.7)-(Fig.8)
  Locked the inner member
 
(4) Locked the inner member Locked the inner member
 
1. Align the outer member and the intermediate member with the baseline.
2. The best distance between outer members and the cabinet should be 2mm.
3. Push the ball retainers between the outer members and the intermediate members to the forefront.
 
 
(5) Push forward the Ball Retainer
  Push the ball retainers between the outer members and the intermediate members to the forefront.(Fig.10)
  Push forward the Ball Retainer
 
(6) Insert drawer members into cabinet members
  Insert drawer members into cabinet members and push the drawer until it is closed. (Fig.10)
  Insert drawer members into cabinet members
 
【Cabinet evaluation check】
  Check the spacing on both sides of the assembled: Please check the 12.7~13.4 if press open the drawer not smooth movement. (Fig.12)
  Cabinet evaluation check
 
   
 
Heavy Duty Slide Silent Soft-Closing AE52/AD52
【Drawer installation guide】
1.
Press the Lever Disconnect to separate slide member
(Fig.1).
2.
Install the inside slides to the drawer member and make sure both of the inside slide are mounted vertically and horizontally parallel(Fig.2).
3.
Install the external slides to the cabinet members and make sure both of the external slides are mounted vertically and horizontally parallel(Fig.3).
4.
Insert the drawer into the cabinet and push the drawer until it is closed(Fig.4).
  Drawer installation guide
 
Drawer installation guide
 
Drawer installation guide
 
Drawer installation guide
 
   
 
Heavy Duty Slide Push-Open AE89/AD89
1. Drawer installation guide
1.
Press the lever disconnect to separate slide members.
(fig.1)
2.
Install the cabinet members as indicated in Fig2. Make sure both cabinet members are vertically and horizontally parallel.(fig.2).
3.
Install the drawer members as indicated in Fig3. Make sure both drawer members are vertically and horizontally parallel(fig.3).
4.
Insert drawer members into cabinet members as indicated in Fig4. and push the drawer untill it is closed.(fig.4).
*
If sound damper is to be used, a distance of 5mm must be reserved for push-open actuation.
*
The center of front panel is suggested as the best push-open point.
  Drawer installation guide
 
Drawer installation guide
 
Drawer installation guide
 
Drawer installation guide
 
Drawer installation guide
 
   
 
 
9256 Concealed Soft Close Hinge for Thick Door
1. Installation Instruction
1.
Please ensure all measurements such as the hole positions and the drilling distances in Fig.1 are met before mounting the hinge.
2.
Please ensure the distance between the door panel and the cabinet is 6mm before mounting the base plate. The hinges and the door edge should be in parallel.(Fig.2)
Installation Instruction
 
2. Installation attention:
Installation skill for two or more hinges
1.
1. Lock all hinges onto the base plates (Fig.3).
2.
2. Push hinge arm 1 and 4 down (Fig.4) until a ‘click’ sound is heard to fix the door.
3.
Press on hinge arm 2 and 3 to complete the installation.
 
Installation attention
 
If the thickness of the door panel is greater than 24mm,
1.
please unscrew the hinge (clockwise) to its maximum potential (Fig.5).
2.
Lock all hinge arms onto the base plates (Fig.3).
3.
Push hinge arm 1 and 4 down (Fig.4) until a "click" sound is heard to fix the door.
4.
Press on hinge arm 2 and 3 until a "click" sound is heard.
5.
Adjust the hinge screw to its optimum position.
6.
To demount the door panel: unscrew the hinge (clockwise) to its maximum potential (Fig.6) and unlock all hinge arms to detach the door panel.
 
Installation attention
 
   
 
Related Services
Product Enquiry
Catalog Download
Contact Us
Freight Rate
Related Support
FAQs
Installation Instructions
Members Center
Member Rights
Distributors Area
Distributor Login
Become a Distributor
About KingSlide Product Info Investor Zone Tech. Support Privacy Policy Site Map
King Slide Linkedin King Slide Google+ King Slide Youtube King Slide Facebook